Bundaberg will soon plug in to new Tesla battery

08 Apr, 2022
Acting Premier Cameron Dick and Member for Bundaberg Tom Smith with some of the Yurika workers who have helped deliver Bargara’s new Tesla battery. Image supplied.

Wide Bay is about to take a step up in Queensland’s renewable energy revolution, with installation of a new grid-connected battery near Bundaberg nearing completion.

Treasurer and Minister for Trade and Investment Cameron Dick said the Tesla battery installation would help residents around Bargara and Bundaberg get the most out of their solar panels.

The Treasurer said: “Queensland has one of the highest rates of rooftop solar installation in the world, and there are times on sunny days when generation far outstrips demand.

“Batteries like this one being installed near Bargara allow us to store that excess energy for use in the evening.

“Bargara is one of five sites chosen across the state in a network-connected battery trial being run by Energy Queensland, along with Hervey Bay, Toowoomba, Townsville and Yeppoon.

“In total, these network-connected batteries will collectively store up to 40 megawatt-hours, enough energy to power 2,400 households.

“The battery, transformer and cables are now all in their final positions in Bargara, with full energisation of the site expected in June.

“Around 18 Energy Queensland staff have helped bring this project to life, but the real sweetener is for the thousands of local residents and businesses around Bargara who stand to benefit from more cheap solar power.”

Bargara and the other battery sites were chosen due to their proximity to existing infrastructure, ensuring lower project costs, faster deployment, and ease of connection to the network.

Member for Bundaberg Tom Smith said the Bargara battery would place the local community firmly at the forefront of the renewable energy revolution.

Smith said: “The Bargara battery will store excess low-cost solar power produced in the middle of the day before supplying it back to the local community during peak consumption in the evening.

“The energy stored in this system is enough to run 478 average homes for one day, which is great news for the local area.

“Distribution-connected batteries will be critical to enabling Queensland’s renewable energy target of 50 per cent by 2030.

“By basing the batteries in the community, it means renewable energy will be generated locally, stored locally, and then used locally, avoiding network energy losses.”

Yurika, part of Energy Queensland, has led the construction for all five network-connected batteries.

Energy Queensland executive general manager Michael Dart said the company was proud to be delivering the Bargara battery system in such a short timeframe.

Dart said: “This is an excellent result for Bargara and the surrounding communities, as they will get access to this network-connected battery very soon.

“The experience Energy Queensland gained from our two previous network-connected battery projects in Townsville has been invaluable as it has meant a very short delivery timeframe for this project here at Bargara.”

Related Articles

Chinchilla battery to charge up Queensland’s energy future

AGL Loy Yang’s proposed battery receives planning approval

Torrens Island

AGL prepares for construction of grid-scale battery at Torrens Island

Comments

Leave a comment Cancel reply

You must be logged in to post a comment.

Latest Posts

  • Energy
  • Construction
  • Resources
30 Jun

AEMO releases energy roadmap to phase out coal generation

30 Jun

Cairns charging up with new network-connected battery

30 Jun

MGA Thermal announces breakthrough in storage technology

29 Jun

Survey shows majority of Australians want investment in renewables

29 Jun

New renewably-powered desalination plant planned for Alkimos

23 Jun

Cities of the future may be built with algae-grown limestone

22 Jun

Global sophisticated green building designs awarded

22 Jun

A national environmental impact standard to measure embodied carbon

15 Jun

Australian cities falling behind global cities on sustainability according to 2022 Sustainable Cities Index

14 Jun

Only timber can tackle climate change – timber and the latest construction technology

29 Jun

Binding methane with metal: a new hope for recycling the potent fossil fuel

29 Jun

WA’s first Clean Energy Future Fund project now operational

29 Jun

New battery and critical minerals prospectus to power investment

29 Jun

Australian-German business coalition produces a roadmap for large scale green hydrogen import to Germany

24 Jun

Farmers say food supply must come before gas export industry

Online Magazine

    Current Cover
  • Login
  • Subscribe

Subscribe

Subscribe to our newsletter

Our Other Titles

  • Home
  • Contact Us
  • Terms and Conditions
  • Privacy
© Sage Media Group 2022 All Rights Reserved.
×
Authorization
  • Registration
 This feature has been disabled
 This feature has been disabled until further notice, however you may still register
×
Registration
  • Autorization
Register
* All fields required