Origin Energy has lodged plans for a major expansion of its grid-scale battery precinct at the site of the Eraring coal-fired power station in New South Wales, proposing to boost the total storage facility capacity to 1,200 megawatts (MW) and 8,600 megawatt hours (MWh).
Origin is seeking federal approval under the Environment Protection and Biodiversity Conservation (EPBC) Act for the Eraring BESS North project.
The proposal seeks to add a grid-scale battery system featuring a discharge capacity of 500 MW and an accessible storage capacity of approximately 4,942 MWh across a 22-hectare footprint on company-owned land in the Lake Macquarie region.
Working alongside the existing State Significant Development-approved battery, the integrated complex will help bridge the state’s emerging firming capacity gap as coal-fired plants retire.
The expansion aligns directly with the NSW Electricity Infrastructure Roadmap targets and the Australian Energy Market Operator’s 2024 Integrated System Plan, which mandates a tripling of grid-scale variable renewable energy by 2030.
The project requires an Environmental Impact Statement (EIS) and involves additional transmission works to connect to TransGrid’s nearby switching station, extension of existing water supply infrastructure, new internal access roads, and operational compounds. Up to 11 hectares of vegetation clearance will be required outside the previously assessed disturbance zone.
Construction will follow a four-phase rollout, beginning with site establishment, bulk earthworks, and foundation concrete slabs, followed by delivery and electrical fit-out of battery enclosures, inverters, and transformers. Temporary infrastructure will include laydown areas, construction compounds, and potential batch plants.
Subject to regulatory approvals, construction is scheduled to commence in 2028 with a planned 2.5-year build period, targeting commercial operations in early to mid-2031. The battery installation has an anticipated operating lifespan of up to 25 years.
Origin confirmed that extensive site selection and stakeholder consultation were conducted to minimise environmental impacts across the construction footprint while supporting the National Electricity Market’s transition towards dispatchable renewable storage.
The Eraring BESS currently includes two main stages of development. Eraring Battery 1 reached the final phase of commissioning in December 2025, while Eraring Battery 2 is under construction and scheduled to come online in the first quarter of 2027.