Goyder South Development Application released for public comment

26 Aug, 2020
Image via. Shutterstock.


The Department of Planning and Transport has released the Development Application for the Goyder South Hybrid Renewable Energy Facility (Goyder South) for public exhibition and comment.

Independent renewable energy producer, Neoen Australia Pty Ltd, is seeking Development Application for the Goyder South pursuant to section 49 of the Development Act 1993 (SA).

The proposed project, to be located south of Burra in the north-west of South Australia, is planned to comprise:

  • A wind farm (up to 163 turbines to a maximum tip height of 240m) with a capacity of up to 1200 Megawatts (MW).
  • A solar farm (across two sites) with a capacity of up to 600MW over 3000 ha.
  • An energy storage facility (lithium-ion battery) with a capacity of up to 900MW/1,800MWh (2 hours).
  • Associated infrastructure for connection to the electricity grid including three substations, access tracks, underground connection cabling and transmission lines.
  • Permanent operations and maintenance compounds.
  • Temporary construction compounds for both wind and solar components, including concrete batching plants.
  • A number of meteorological masts (in addition to those already on the site) to record wind speed and other meteorological data, both pre- and post-construction.

 

At its full size of approximately 1200MW of wind, 600MW of solar and 900MW/1,800MWh of battery storage, Goyder South could generate more than 4,800,000 MWh of power annually [1] estimated to be equivalent to:

  • 2,112,000 tonnes of CO2 avoided per year.
  • 872,000 cars taken off the road per year.
  • 39,360,000 trees planted per year.

 

Given the scale of energy generation which would be achieved by the project, Goyder South is proposed to be constructed across multiple stages (potentially three separate stages each comprising 400MW wind, 200MW solar, and 300MW/600MWh storage).

Neoen requests that, if approved, the development timeframes be structured on a rolling basis and expects that the construction of the entire large-scale project could be completed within 12 years from the date of approval.

The Development Application can be downloaded via the State Commission Assessment Panel (SCAP) site. Please look under ‘Crown Developments’, Development Number 422/V009/20, Neoen Australia Pty Ltd.

Neoen encourages all local residents to have their say on the project. If you would like to submit a representation to SCAP, information and forms can be found at the above link. Note that the closing date for representations is 18 September 2020.

Neoen also invites community members with questions, comments or concerns to call the project hotline 1800 966 166 or send a message to contact@goyderenergy.com.au

Share this story

  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook

Related Articles

Smart Energy South Australia

Australia Wind Energy 2025

Floating Wind - Europe

Floating Wind – Europe

The 5th Australian Offshore Wind Conference

The 5th Australian Offshore Wind Conference

Comments

Leave a comment Cancel reply

You must be logged in to post a comment.

Breaking

  • Energy
  • Construction
  • Resources
10 Feb

Hiringa Energy reaches financial close for Kapuni project

09 Feb

Iberdrola completes battery storage project in Sydney

09 Feb

Australia launches inquiry into solar recycling

09 Feb

Warradarge expansion powers WA’s renewable transformation

06 Feb

Energy Vault’s NSW BESS project lands long-term service agreement

09 Feb

NSW government showcases net zero home to help lower energy bills

06 Feb

Construction industry pushes for freight and carbon efficiency

04 Feb

River Capital, CEFC invest in Tiwi Islands Plantation carbon project

30 Jan

VEU accreditation revoked for Save Energy Solutions following breach

29 Jan

Research shows support for office repurposing, but awareness gaps persist

10 Feb

Miner adds a little zest to its environmental zing

10 Feb

Australia and Japan forge graphite supply partnership

06 Feb

Australia’s mining diesel emissions keep rising

05 Feb

Australian Renewable Energy Hub lands AU$21 million ARENA funding

05 Feb

Australian government unveils details of Net Zero Fund

Online Magazine

    Current Cover
  • Login
  • Subscribe

Subscribe

Subscribe to Newsletter

Our Titles

  • Share on Newsletter
  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook
  • Home
  • Contact Us
  • Terms and Conditions
  • Privacy
© Sage Media Group 2026 All Rights Reserved.
×
Authorization
  • Registration
 This feature has been disabled
 This feature has been disabled until further notice, however you may still register
×
Registration
  • Autorization
Register
* All fields required