Competitive tender for firming infrastructure and demand response

03 Apr, 2023
tender



AEMO Services has launched its second competitive tender, seeking at least 380 megawatts (MW) of additional firming infrastructure located within the Sydney-Newcastle-Wollongong sub-region before 1 December 2025.

AEMO Services was directed to conduct this competitive tender for firming infrastructure because of the announcement of the earlier than previously scheduled closure of the Eraring Power Station.

“Firming infrastructure is a critical component of any reliable power system and will be needed when intermittent generation resources, like wind and solar, are not available,” said Executive General Manager of AEMO Services, Paul Verschuer.

Technologies eligible for this tender round must be scheduled, meaning there is control over when they deliver power to the grid. This includes a broad range of energy supply resources, like grid-scale batteries, pumped hydro, gas and biofuel generators. Demand response is also eligible, so for the first time in Australia newbuild infrastructure assets will compete with demand response to deliver firming infrastructure.

“Demand response is an innovative, cost-effective solution already being used widely around the world. It encourages businesses to reduce their consumption during periods of high demand and get paid to do this.

This helps free up supply to the market, while reducing the overall need to build new infrastructure, which ultimately drives down costs for consumers,” said Mr Verschuer.

Any new firming infrastructure developed will need to provide energy to the Sydney-Newcastle-Wollongong sub-region during times of peak consumer demand. Demand response applicants will have to be located within the sub-region to be eligible for a demand response contract.

“By developing firming infrastructure in the Sydney-Newcastle-Wollongong sub-region, we can ensure this new infrastructure will deliver power right where it’s needed, alleviating the pressure on our existing transmission system until new power lines can come online,” said Mr Verschuer.

This is the second competitive tender announced by AEMO Services, following the inaugural tender in October 2022, which has already attracted 4,300 MW of potential generation and long-duration storage projects.

“Our first tender demonstrated a strong interest from the market to invest in New South Wales, and we’re excited to use our second tender round to support a more cost-effective, reliable energy system for New South Wales consumers,” said Mr Verschuer.

Project bids will close on 18 May 2023.

Share this story

  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook

Related Articles

Horizons Clean Energy Expansion Week 2026

Horizons Clean Energy Expansion Week 2026

All Energy Australia

All Energy Australia

smart energy south australia

Smart Energy South Australia

Energy Storage Summit Asia 2026

Comments

Leave a comment Cancel reply

You must be logged in to post a comment.

Breaking

  • Energy
  • Construction
  • Resources
17 Aug

Energy firms explore mines for long-duration grid storage

17 Aug

BW ESS acquires Yanco energy storage system in New South Wales

14 Aug

Researchers nears solution to solar panel waste problem

13 Aug

Australia’s green fund commits $105B in clean energy projects  

13 Aug

Cheaper silver recovery could end solar panel landfill dumping

12 Aug

U.S. Green Building Council appoints David Purcell as CMO

05 Aug

NSW backs large-scale hemp manufacturing for housing with $2m grant

31 Jul

Closure of NSW lighting scheme creates gap for warehouses and industrial sites

29 Jul

Stockland launches first net-zero energy village Ampére

28 Jul

NSW expands Greener Neighbourhoods Grants to combat urban heat

14 Aug

Australian Vanadium, Alcoa partner to explore vanadium battery system for WA refineries

05 Aug

KETH project nears operation after award of EPC contract

05 Aug

Mining sector performance proves renewables work at scale

03 Aug

Investors favour flexible biopower over simple generation projects

29 Jul

Researchers find microbes turn mining waste into mobile nanoparticles

Online Magazine

    Current Cover
  • Login
  • Subscribe

Subscribe

Subscribe to Newsletter

Our Titles

  • Share on Newsletter
  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook
  • Home
  • Contact Us
  • Terms and Conditions
  • Privacy
© Sage Media Group 2026 All Rights Reserved.
×
Authorization
  • Registration
 This feature has been disabled
 This feature has been disabled until further notice, however you may still register
×
Registration
  • Autorization
Register
* All fields required