Kidston pumped hydro on track for energisation in 2024

23 May, 2023
K2-Hydro
Image of Kidston’s two pits taken in October 2017, credit: Genex Power.


Genex Power Limited (ASX:GNX) is continuing construction activities at the 250 megawatt/2,000 megawatt-hour Kidston Pumped Storage Hydro Project, which remains on track for energisation in the second half of 2024.

Following continued excavation works in favourable ground conditions, the powerhouse cavern roof has now been fully excavated.

The focus of works is now on a program of rock bolting and shotcreting the wall structures before the works will step down to commence the first bench excavation.

Concurrently, works for excavation of the construction adits and Main Access Tunnel continue to progress also in very favourable ground conditions.

The ventilation shaft has also now been completed with the raisebore machine currently progressing the electrical cable shaft, which is the second of four vertical shafts.

Significant progress continues to be made on the Powerlink 275kV transmission line from Kidston to Guybal Munjan (Mt Fox) and associated connection infrastructure.

Since Genex’s 29 March 2023 announcement, the following key activities have taken place:

  • Concrete foundations and steel erection for the transmission line lattice towers have commenced;
  • Strong progress continues at Guybal Munjan substation with the installation of civil foundations and below ground conduits for the commencement of civil earthworks;
  • Preparation works have continued for the Aurumfield substation at Kidston (K2X) with pad subgrade works nearing completion;
  • Major procurement is complete, with the long lead time shunt reactors for both Guybul Munjan and Aurumfield now in Australia;
  • Progression of the K2H switchyard with the installation of the control room and ongoing works associated with the installation of primary steelwork, equipment and cabling; and
  • Completion of the major concrete foundations for the four transmission line monopoles between K2H and Aurumfield, the largest being a 220-cubic-metre single concrete pour.

Share this story

  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook

Related Articles

Comments

Leave a comment Cancel reply

You must be logged in to post a comment.

Breaking

  • Energy
  • Construction
  • Resources
14 Jan

Solar and wind farms spill power amid oversupply

14 Jan

Neoen advances 500 MW Wheatbelt wind project

12 Jan

First stage of Eraring battery starts commercial operations

09 Jan

Japan’s first floating offshore wind farm starts operations

09 Jan

Vestas powers South Australia’s clean future

14 Jan

2025 marked peak Green Star sustainability in Australian buildings

19 Dec

RICS report shows AI could boost green infrastructure

17 Dec

CEFC urges investors to lead green data centres growth

12 Dec

Queensland offers renters, landlords rebates for solar power use

12 Dec

NSW government grants $25.45M to reduce cement emissions

14 Jan

‘Breathing batteries’ store energy and carbon

14 Jan

New project advances Iron Nitride magnet production

19 Dec

Airbridge secures AU$1.5 million grant for carbon dioxide capture project

19 Dec

Study finds Australian organisations place technology central to climate action

15 Dec

Flinders University researchers search solutions for mine waste

Online Magazine

    Current Cover
  • Login
  • Subscribe

Subscribe

Subscribe to Newsletter

Our Titles

  • Share on Newsletter
  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook
  • Home
  • Contact Us
  • Terms and Conditions
  • Privacy
© Sage Media Group 2026 All Rights Reserved.
×
Authorization
  • Registration
 This feature has been disabled
 This feature has been disabled until further notice, however you may still register
×
Registration
  • Autorization
Register
* All fields required