Renewable energy developer Edify Energy has referred its proposed 800-megawatt Glenarbon solar power station and battery project in southwest Queensland for federal environmental assessment.
Submitted under the Commonwealth Environment Protection and Biodiversity Conservation (EPBC) Act, the development is located roughly 65 kilometres east of Goondiwindi within the Southern Queensland Renewable Energy Zone.
The project pairs an 800 MW single-axis tracking solar photovoltaic farm with an 800 MW, four-hour (3,200 MWh) battery energy storage system designed to store excess solar generation and supply the grid during peak demand.
Spanning a 1,973.1-hectare project area, the facility will have a maximum disturbance footprint of 1,543.2 hectares across largely non-remnant, degraded land, while setting aside 429.9 hectares as an avoidance zone to protect key environmental values.
The power station will connect directly into the National Electricity Market via a new T-connection to an existing Powerlink 330 kV transmission line traversing the site.
Alongside the generating and storage infrastructure, Edify plans to upgrade Bosnjaks Road where it crosses Macintyre Brook, straightening entry angles and replacing an existing concrete causeway to accommodate heavy construction vehicles while improving local flood resilience and fish passage.
To ease pressure on regional housing, the developer also intends to build temporary on-site accommodation for up to 600 full-time equivalent construction workers.
Expected to operate for around 50 years before being decommissioned and returned to its original state, the facility is projected to generate up to 1,555 gigawatt-hours of clean electricity annually.
Edify is simultaneously preparing a state development application for Queensland’s State Assessment and Referral Agency. Public comments on the federal EPBC referral remain open until 29 November.