AGL firms up supply with Broken Hill grid-scale battery

29 Sep, 2021
grid-scale



AGL’s proposed grid-scale battery in Broken Hill has made another major step forward with the NSW Department of Planning, Industry and Environment (DPIE) granting approval for up to 50 megawatts (MW), 100 megawatt-hour (MWh) project.

The battery system will help to improve the reliability of energy supply in Broken Hill, as well as providing storage and firming capacity to the National Energy Market (NEM).

AGL Chief Operating Officer, Markus Brokhof said is developing an 850 MW network of batteries to add flexibility to Australia’s energy supply.

“With the green light on planning, we can now proceed to investment decision – another important step to become the leading orchestrator of batteries,” Mr Brokhof said.

“The limiting factor for renewable technology has always been storage but we are taking control of these constraints by turning our attention to firming technology, like batteries.

“Batteries and energy storage are critical to supporting the increased growth of renewable generation and in turn driving downward pressure on wholesale electricity prices.”

AGL developed one of Australia’s largest utility-scale solar plants in 2016 and the Silverton Wind Farm in 2018.

“Together these assets, provide more than 250 MW of capacity and power around 158,000 average Australian homes.

The project will be located on industrial land, near the Broken Hill substation and around 6 km southeast of the Broken Hill airport.

A final investment decision on the project is subject to the finalisation of contracts and approvals. Construction is expected to begin later this year, with commissioning planned for 2023.

Share this story

  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook

Related Articles

Battery Show

The Battery Show Asia – Indonesia

Battery Asset Management Summit 2025

Battery Asset Management Summit Australia

Aggreko

Comments

Leave a comment Cancel reply

You must be logged in to post a comment.

Breaking

  • Energy
  • Construction
  • Resources
14 Jan

Solar and wind farms spill power amid oversupply

14 Jan

Neoen advances 500 MW Wheatbelt wind project

12 Jan

First stage of Eraring battery starts commercial operations

09 Jan

Japan’s first floating offshore wind farm starts operations

09 Jan

Vestas powers South Australia’s clean future

14 Jan

2025 marked peak Green Star sustainability in Australian buildings

19 Dec

RICS report shows AI could boost green infrastructure

17 Dec

CEFC urges investors to lead green data centres growth

12 Dec

Queensland offers renters, landlords rebates for solar power use

12 Dec

NSW government grants $25.45M to reduce cement emissions

14 Jan

‘Breathing batteries’ store energy and carbon

14 Jan

New project advances Iron Nitride magnet production

19 Dec

Airbridge secures AU$1.5 million grant for carbon dioxide capture project

19 Dec

Study finds Australian organisations place technology central to climate action

15 Dec

Flinders University researchers search solutions for mine waste

Online Magazine

    Current Cover
  • Login
  • Subscribe

Subscribe

Subscribe to Newsletter

Our Titles

  • Share on Newsletter
  • Share on LinkedIn
  • Share on Twitter
  • Share on Facebook
  • Home
  • Contact Us
  • Terms and Conditions
  • Privacy
© Sage Media Group 2026 All Rights Reserved.
×
Authorization
  • Registration
 This feature has been disabled
 This feature has been disabled until further notice, however you may still register
×
Registration
  • Autorization
Register
* All fields required