UNStudio, with local partner HYP Architects, were recently announced by the Atenor, Arhs group and Agora Luxembourg as the winners in the competition for the design of the Kyklos building in Belval, Luxembourg, and have found a hybrid steel-concrete design would provide the lowest carbon footprint.
Belval is a redevelopment project that has successfully transformed an old industrial site in Luxembourg into an urban centre that now houses a university and technological centre, residential and office spaces, in addition to hotels and retail. The Kyklos building will be the last building to shape the Central Square district.
While in recent years the focus when designing new builds has been firmly placed on operational carbon emissions, in fact in the first approximately 40 years, only 10 per cent of a building’s carbon footprint is determined by its operational use.
Ninety per cent is determined by the materials used – so while operational carbon remains an essential concern, for the design of the Kyklos building, great effort was made to consider the entire (whole life) carbon footprint.
Developing the right tools
UNStudio is currently in the process of developing a fully-fledged sustainable design framework that, alongside other applications, enables their designers to have full control of the embodied carbon impact of the designs.
As part of this set of tools, the ‘Carbon Builder’ makes it possible for designers to intricately study numerous options to reduce the carbon footprint of their projects.
For the Kyklos building proposal, using the early prototype of the Carbon Builder enabled the team to make the correct decisions early in the concept design process.
By assessing the embodied carbon, it was possible to reduce the carbon footprint of the design concept for this building by around 80% compared to a traditional office building in Luxembourg.
Selecting the best materials
The possibility of using steel with 100 per cent recycled content and working with best practice concrete mixtures, improved the carbon performance of the project significantly.
Set against the function-use demands, this resulted in the choice of a hybrid steel-concrete structure over other construction methods.
It was determined that this hybrid solution offered a better carbon performance in the long run. The early best possible roadmap shows the ultimate possibility of achieving 115 kilograms of carbon dioxide equivalent per square metre, compared to 580 kilograms per square metre for a typical office building in Luxembourg.
The Kyklos building is anticipated to achieve BREEAM Outstanding and WELL Platinum certifications.
UNStudio Founder and Principal Architect Ben van Berkel said: “Our new carbon tools have shown us that timber is not always the best option and that highly sustainable buildings do not all have to look the same.
“We can now demonstrate that interesting geometry and high levels of sustainability are not mutually exclusive.”
Kyklos (the Greek word for ‘circle’) is the last building in the large development taking place in Belval, Luxembourg. The building is intended to be the centerpiece of the Agora Masterplan and is strategically located in the centre of the development, next to ‘Place des Bassins’.
The emblematic design of the Place des Bassins connects two basins – remnants of the former steelworks site on which the district is developed – in the form of a singular ‘infinity loop’. This loop symbolises the alliance of the industrial site and its revitalisation as an urban space. Due to its proximity to the square, the building is envisioned as the third loop in this equation: a sustainable connection that represents the future of the urban development.
Urban integration and a holistic sustainable approach are the two main drivers of the design of all elements of the building, from its functional organisation to its construction techniques and its materiality.
From the beginning of the design process, the goal was to highlight the unique elements of the site and create a building whose form could clearly and uniquely be linked to these features. The design takes into account the master plan, the main pedestrian path and the existing main square, to create a building that is inspired by and complements its surroundings. The result is the combination of the circular geometry of the square with the orthogonal geometry of the surrounding buildings.
With a total surface area of 7,600 square metres above ground and a basement of 2,250 square metres, the Kyklos building offers eight floors of office space above a mixed-use lower level. Numerous strategies are incorporated into the design to ensure high levels of transparency and daylight. One corner of the building is setback on the lower levels, creating an overhang that further serves to protect from overheating.
The lobby is designed as a unified space comprising both the main reception and commercial functions that are directly accessible from inside and outside. From here a large, circular staircase forms a visual connection with the Place des Bassins outside, while encouraging users of the building to use the stairs, rather than the elevators.
The floor plates of the Kyklos building branch from the circular core and are suspended from steel cables. This eliminates the need for load bearing columns as much as possible and frees up the floors for a variety of possible interior layouts. The design of the building also ensures flexibility for possible use changes in the future.